CABP High Tech Park Pty Ltd (CABP) has unveiled plans for Hunter
Horizon Park, an integrated technology and renewable energy precinct
incorporating a 300 MW data centre, 100 MW solar farm and 450 MW / 900 MWh
battery energy storage system in the NSW Hunter region.
The development is proposed on approximately 230 hectares of land currently used as a commercial pine plantation at Heatherbrae, near Raymond Terrace in the Port Stephens local government area.
The proposed modular data centre would have an IT load capacity of up to 300 MW, with the solar farm distributed across four precincts within the development site. Renewable electricity generated on-site would support data centre operations and battery charging, with surplus electricity potentially exported to the grid.
The two-hour duration BESS would be accommodated within a dedicated compound, with associated electrical infrastructure including an on-site sub-station.
Grid connection studies are underway with Ausgrid, with the indicative concept plan identifying a proposed 132kV connection. Emergency backup generation is also proposed.
Despite the proposed on-site renewable electricity generation and storage capacity, Hunter Horizon Park is expected to require substantial external electricity supplies to support its 300 MW IT load. CABP has not publicly identified any additional renewable energy developments or power purchase agreements, although the precinct’s location within the Hunter–Central Coast Renewable Energy Zone could facilitate such arrangements.
The proposed 900 MWh BESS could also support compliance with the NSW Government’s new data centre renewable energy and storage guidelines.
CABP is preparing an Environmental Impact Statement for the development, which will be assessed under the NSW State Significant Development planning pathway.
The company is commencing community consultation with public information sessions held this week, followed by an online webinar on 9 December.